North Strathfield Rail Underpass

The project involved the construction of a rail underpass tunnel at North Strathfield station and upgrades to North Strathfield and Concord West Stations

Client: Arenco / John Holland

Duration: Jun 2013

Scope of Works:

  • Civil & Tunnel were engaged by Arenco / John Holland to supply plant, labour and supervision during two time critical track possessions to demolish and renew approximately 80m of existing station platform at Concord West station using precast culverts. The culverts were 2.4m x 1.2m x 1.8m.
  • The excavators (13 ton and 5 ton) were lifted onto the platform and the culverts and deck slabs were lifted into position using a 300t crane over the existing platform buildings.