Liverpool Turnback

Project:

The project involved the construction of additional track at Liverpool Station.

Client:

John Holland

Duration:

Jan 2012

Civil & Tunnel’s Scope of Works:

  • Civil & Tunnel were contracted by John Holland  to excavate and install 1km of HDPE track drainage ranging in size from 300-600mm during a 10 day time critical track possession, including nightshift works.

  • The alignment of the pipeline was  underneath the ballast shoulder of the existing track to depths of 3m, which required the use of shoring boxes to support the saturated ground. 